Project location: Houli Dist., Taichung City
Contract value: $341,660,000 TWD
Final payment amount: $367,689,159 TWD
Contract duration: 416 days
Approved duration: 493 days
Commencement date: 2017-04-21
Completion date: 2018-08-25
Proprietor: Taichung City New Construction Office
Design and Supervision: Xie Sheng Engineering Consultants Ltd.
Construction: Earth Power Construction Co., Ltd.