Project location: Annan and North District, Tainan City
Contract value: $433,000,000 TWD
Final payment amount: $462,958,517 TWD
Contract duration: 910 days
Approved duration: 1,186 days
Commencement date: 2016-08-10
Completion date: 2019-11-01
Proprietor: West Coast Expressway Southern Region Engineering Office, Directorate General of Highways, Ministry of Transportation and Communications
Design: T.Y.Lin Taiwan Consulting Engineers inc.
Supervision: Second Branch, West Coast Expressway Southern Region Engineering Office, Directorate General of Highways, MOTC
Construction: Earth Power Construction Co., Ltd.